Second floor's subfloor is ready and almost all the wall's framing is done. Still missing the walls from bedrooms two and three because we are waiting for the window headers which didn't arrived from TW Perry on time.
Roger has been working in preparing the stone wall openings for the new windows. David Hawkins has to come and re-measure before ordering them.
Roger has been working in preparing the stone wall openings for the new windows. David Hawkins has to come and re-measure before ordering them.